Extra Technicians Needed to Finish the Fiber-Optic Cable on Schedule A logistics firm planned to lay an 8 km fiber-optic cable in 240 days. For this task, it initially deployed 160 technicians. After 80 days, the firm reviewed progress and found that only 2 km of cable had been laid. How many additional technicians must be deployed so that the remaining work is completed exactly on schedule?